NOTE: You may place the mouse over a location to see its municipality and county,
or click on the location to see a map of the event.
I-90 EB (Regional)
| at South Junction I-39/90/US-51
|
17.3 |
None |
All lanes and shoulders open |
03/28/13 07:00 AM to 12/31/14 11:59 PM |
IDOT |
Size & Weight restrictions - Obtain required permit from Toll Authority 630-241-6800. Max height: 14 ft 6 in, max width 12 ft 0 in |
| Exit to Genoa Rd
|
25.2 |
Minor |
Ramp work, possible width reduction |
04/15/13 07:00 AM to 10/06/13 11:59 AM |
Illinois Tollway |
Shoulder Widening; Right Side Ramp Closed; ***Long Term Closure*** |
| Entrance from Genoa Rd
|
25.2 |
Minor |
Ramp work, possible width reduction |
04/15/13 07:00 AM to 10/06/13 11:59 AM |
Illinois Tollway |
Shoulder Widening; Right Side Ramp Closed; ***Long Term Closure*** |
| Exit to US-20
|
41.7 |
Medium |
Ramp work, possible width reduction |
04/25/13 06:00 AM to 07/20/13 11:59 PM |
Illinois Tollway |
Right Side of Ramp Closed; Pavement Reconstruction; ***Long Term Closure*** |
| Entrance from US-20
|
41.7 |
Medium |
Ramp work, possible width reduction |
04/25/13 06:00 AM to 07/20/13 11:59 PM |
Illinois Tollway |
Right Side of Ramp Closed; Pavement Reconstruction; ***Long Term Closure*** |
| Entrance from Cermak Rd
|
54.6 |
Minor |
Left lane and left shoulder closed, two or three lanes open with ramp work, possible width reduction |
04/08/13 09:00 PM to 09/20/13 11:59 PM |
IDOT |
On Chinatown Feeder; ***Long Term Closure*** |
| County Road 150 N to Sycamore Rd
|
45.0 to 69.0 |
Minor |
All lanes and shoulders open |
05/20/13 12:01 AM to 05/26/13 11:59 PM |
Indiana Toll Road |
12' width restriction only |
I-90 WB (Regional)
| Quince Rd to County Road 150 N
|
69.0 to 45.0 |
Minor |
All lanes and shoulders open |
05/20/13 12:01 AM to 05/26/13 11:59 PM |
Indiana Toll Road |
12' width restriction only |
| Exit to EB I-94
|
21.1 |
Medium |
All lanes and shoulders open |
01/03/11 07:00 AM to 01/06/14 11:59 PM |
Indiana Toll Road |
No lanes closed, Exit 21 WB 12 ft width restriction |
| Entrance from EB I-80
|
20.4 |
Medium |
All lanes and shoulders open |
03/14/11 07:00 PM to 01/06/14 11:59 PM |
Indiana Toll Road |
Lake Station - EB Exit from 80/94 to ITR Bridge: No lanes closed, 14 ft width restriction |
| Ramp from NWB I-90 (Chicago Skwy) to Dan Ryan Express
|
|
Medium |
All lanes and shoulders closed |
04/01/13 07:00 AM to 07/15/13 11:59 PM |
IDOT |
Entrance to Dan Ryan Express Lanes from Chicago Skyway closed - all traffic diverted to Local Lanes. **Long Term Closure** |
| Marquette to 63rd St
|
59.3 to 58.7 |
Minor |
Left shoulder closed, all lanes open |
04/01/13 07:00 AM to 07/15/13 11:59 PM |
IDOT |
***Long Term Closure in locals*** |
| Exit to Genoa Rd
|
25.6 |
Minor |
Ramp work, possible width reduction |
04/09/13 07:00 AM to 10/06/13 11:59 PM |
Illinois Tollway |
Right Side of Ramp Closed; Landscaping; Material Storage; ***Long Term Closure*** |
| Entrance from Genoa Rd
|
25.6 |
Minor |
Ramp work, possible width reduction |
04/09/13 07:00 AM to 10/06/13 11:59 PM |
Illinois Tollway |
Right Side of Ramp Closed; Landscaping; Material Storage; ***Long Term Closure*** |
| Irene Rd to Mill Rd
|
20.8 to 17.7 |
Medium |
Left lane shifted, one lane closed |
04/17/13 05:00 PM to 10/06/13 11:59 PM |
Illinois Tollway |
Pavement Widening; Traffic shift; ***Long Term Closure*** |
| at South Junction I-39/90/US-51
|
17.3 |
None |
All lanes and shoulders open |
03/28/13 07:00 AM to 12/31/14 11:59 PM |
IDOT |
Size & Weight restrictions - Obtain required permit from Toll Authority 630-241-6800. Max height: 14 ft 6 in, max width 12 ft 0 in |